QuantlibXL: multiple calls to qlSetEvaluationDate()

Posted by Wilkie Lai on
URL: http://quantlib.414.s1.nabble.com/QuantlibXL-multiple-calls-to-qlSetEvaluationDate-tp5043.html

Hi Eric and all,
1.) I have experienced strange behavior with
qlSetEvaluationDate().  As I read from the
documentation there is only one global setting for
this variable in Excel so I would assume that once a
call to this function has been made, the evaluation
date will remain the same unless a different parameter
is passed to it.  However I have come to notice that
with multiple calls to this function it actually set
the global date to another date, seems like a
hard-coded one: 2005/06/18.  Can anyone share what is
going on behind the scene?

2.) Now because of this change in evaluation date I am
forced to do global recalculate (Ctrl-Alt-Shift F9,
usual Ctrl-Alt-F9 don't work) in order to fix the
date, but after multiple calls (usually 3-4 times)
then Excel will crash, pointing again to the XLL
library.  Would this be a  bug or there are other ways
to change/restate the evaluation date?